Churchill River desk · Tracker

What's signed. What's open. What we still mark unknown.

August's cooperation agreement is a . The September House vote (21–18) is a political yes. The contracts that lock the power are still ahead, and the Premier has not promised MHAs a vote on them.

Last verified public documents onlyUNKNOWN labelled

Gates on the Churchill Falls framework, with today marked17 AugFramework signed17 SepHouse endorsed 21–185 OctQuébec votes31 DecBinding target31 MarFramework term ends

On paper

5

Cooperation paper signed

Framework17 Aug 2026

NL Hydro, Hydro-Québec, and CF(L)Co signed a cooperation paper in August. It is a framework for writing later contracts — not the contracts that lock the power.

House said yes 21–18

Endorsed17 Sep 2026

The House said yes 21–18 after a special sitting, with no referendum. That is a political yes. It does not write power-purchase contracts.

Gull Island size is still a range

FrameworkMaterial Terms as of 17 Aug 2026

Public paper describes a new Churchill River plant in a range — not one locked size — and says studies still have to finish. First power is pencilled for the mid-2030s. Do not treat a press headline as a commissioned megawatt.

Upgrades to the existing plant

FrameworkAnnex B as of 17 Aug 2026

The paper also talks about upgrading the existing Churchill Falls plant over time. The year-by-year megawatts in the annex are a joint preliminary picture — they move if the projects move.

New line to the mining corridor

FrameworkAug 2026 announcement + Hydro study

The mining corridor from Churchill Falls to Labrador West is already tight. The August announcement attaches money to a new line. Engineering and permits are under way this fall. Nobody has published when it switches on.

Open

7

Back to the House — but no promised vote

Open18 Sep 2026

The Premier says the deal comes back to the House before the binding contracts are signed. He has not said MHAs will get a vote. The next decision point may have no vote attached.

Binding contracts still unsigned

Open~31 Dec 2026 / term to ~31 Mar 2027

The parties say they want the real contracts around year-end. The framework clock can run into March 2027 unless they replace or extend it. While it runs, Hydro-Québec holds exclusive rights on Gull Island.

Québec votes 5 October

Open5 Oct 2026

The next public political gate is the Québec election. It is not an NL door you can walk through. The party that signed the paper is running third in the polls, and the front-runner has said it does not plan to tear the deal up — but it wants time to study it.

Innu Nation issues still open

Open15–21 Sep 2026

Innu Nation urged MHAs not to vote and says the paper cuts its benefits by more than half. The Premier said outstanding issues need to be resolved and that he looks forward to sitting down. Partnership remains open. As of 21 September the Grand Chief said the Innu are ready to meet, no meeting is scheduled, and it is always the Innu reaching out. Nothing large on that land proceeds without that work.

Innu in Québec say consent is mandatory

OpenAug 2026 — ongoing

Innu communities on the Québec side say their consent is required too, and their older court case over Churchill Falls is still alive. That is a second Indigenous file on the same river.

Inflation path is not a market path

OpenMaterial Terms Annex F · LAB-IND-1

Export payments on the new paper move with a Canadian inflation band. Labrador industrial energy already splits a development block from a market block. Those are different machines. Do not mash them into one “cheap power” number.

Unused retain already has a buyer

OpenMaterial Terms §4

If NL does not use retained power at home, the paper already names ways Hydro-Québec can buy it — including a discounted default if there is no three-year notice. Leftover megawatts do not sit still by magic.

Not published

3

Wind company not named

UNKNOWNDCIA Schedule B §7

A large Labrador wind study sits in the paper. The company that would own it is not named. Do not invent a name, a dollar figure, or a federal share.

No public year-by-year meter

UNKNOWNStill open in public text

The public still does not have a year-by-year meter of who gets retained power. A headline retain number is not a schedule.

What “used here” means is still thin

UNKNOWNStill open in public text

The paper says retained power is for “domestic load” — and then lists ways leftover power can be sold west. What “used here” means in words a voter can check is still thin.

Annex B

New megawatts are a decade out. The contracts are months out.

Annex B preliminary rampChurchill Falls upgrades ramp from 464 MW in 2035 to 1,275 MW in 2042. Gull Island first volumes of 1,350 MW in 2036 and 2,700 MW from 2037 in the 2,700 MW case. All preliminary.01,0002,000MW203420352036203720382039204020412042preliminary · Annex B · subject to studies
  • Gull Island (2,700 MW case):
  • Churchill Falls upgrades:

New megawatts are a decade out. The contracts that decide who gets them are months out.

Civic watchlist / moderated wall is not this page. Corrections: tom@openpeople.ai. Also: Industries · Costs · Evidence brief.